The amount of work in a leather factory is increased by 50%. By what percentage is it necessary to increase the number of workers to complete the new amount of work in previously planned time, if the productivity of the new labour is 25% more?
A. 60%
B. $66\dfrac{2}{3}\% $
C. 40%
D. $33\dfrac{1}{3}\% $
Answer
226.5k+ views
Hint: Let us consider that initially there were 100 men in the factory and the planned time is 1 unit. Find the amount of work by the formula ${\text{men}} \times {\text{time = work}}$. Find the required number of men for the new work according to the given relation.
Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the ${\text{men}} \times {\text{time = work}}$
Substitute the value 100 for men and 1 for time , we get work as
$100 \times 1 = 100$
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is $100 + 50 = 150$.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula ${\text{men}} \times {\text{time = work}}$.
${\text{men}} \times {\text{1 = 150}}$
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is $150 - 100 = 50$ .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is \[50 - 0.25 \times 50 = 40\].
Thus the actual requirement for new men is 40.
Percentage requirement of new men is \[\dfrac{{40}}{{100}} \times 100 = 40\% \], as the initial number of labour was 100.
Thus option C is the correct answer.
Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, ${\text{men}} \times {\text{time = work}}$. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Complete step by step answer:
Let us consider that initially there were 100 men in the factory and the planned time is 1 unit.
We know that the ${\text{men}} \times {\text{time = work}}$
Substitute the value 100 for men and 1 for time , we get work as
$100 \times 1 = 100$
These parameters represent the initial value of the factory.
According to the question, the work in the factory has increased by 50%.
Thus the new work will be initial work + 50% of initial work
The value for initial work was calculated as 100.
Therefore the new work is $100 + 50 = 150$.
We have to complete the work in the previous planned time, that is 1 unit. Therefore the number of men required can be calculated from the formula ${\text{men}} \times {\text{time = work}}$.
${\text{men}} \times {\text{1 = 150}}$
Total men required = 150
However 100 men are already present in the factory. Thus the number of new men required is $150 - 100 = 50$ .
We are given that the efficiency of new men is 25% more than the already present men. Thus, the new men should be hired 25% less.
That is \[50 - 0.25 \times 50 = 40\].
Thus the actual requirement for new men is 40.
Percentage requirement of new men is \[\dfrac{{40}}{{100}} \times 100 = 40\% \], as the initial number of labour was 100.
Thus option C is the correct answer.
Note: The number of times required and the number of men is directly proportional to the amount of work done, that is, ${\text{men}} \times {\text{time = work}}$. Percentage requirement is calculated as 40% in this question, which means the factory requires 40% more men of the total men in the factory.
Recently Updated Pages
Mutually Exclusive vs Independent Events: Key Differences Explained

Area vs Volume: Key Differences Explained for Students

Wheatstone Bridge – Principle, Formula, Diagram & Applications

Types of Solutions in Chemistry: Explained Simply

States of Matter Chapter For JEE Main Chemistry

List of Top 5 Engineering Colleges in Bangalore

Trending doubts
JEE Main 2026: City Intimation Slip and Exam Dates Released, Application Form Closed, Syllabus & Eligibility

JEE Main 2026 City Intimation Slip Live (OUT): Paper 1 & Paper 2 Exam Dates Announced

JEE Main Syllabus 2026: Download Detailed Subject-wise PDF

JEE Main Marks vs Percentile 2026: Calculate Percentile and Rank Using Marks

JEE Main 2026 Admit Card LIVE: Session 1 Hall Ticket Download Link Soon @ jeemain.nta.ac.in

JEE Main 2026 Exam Centres (OUT) – Latest Examination Centre and Cities List

Other Pages
Pregnancy Week and Due Date Calculator: Find How Far Along You Are

NCERT Solutions For Class 10 Maths Chapter 11 Areas Related to Circles (2025-26)

NCERT Solutions For Class 10 Maths Chapter 12 Surface Areas and Volumes (2025-26)

All Mensuration Formulas with Examples and Quick Revision

Complete List of Class 10 Maths Formulas (Chapterwise)

NCERT Solutions for Class 10 Maths Chapter 13 Statistics